Construction Updates

Built in the open.

A public, month-by-month record of construction across every active Mill Hill project.

Construction Updates

Dubai Islands

Allegro Residences

Sold OutProject page

January 2026

88%

Vertical columns and upper deck formwork advancing

Site progress January 2026 view 1Site progress January 2026 view 2Site progress January 2026 view 3Site progress January 2026 view 4Site progress January 2026 view 5Site progress January 2026 view 6

December 2025

84%

Structural works continuing on upper levels

December 2025 site view 1December 2025 site view 2December 2025 site view 3December 2025 site view 4

November 2025

82%

Vertical columns and upper deck formwork underway

November 2025 site view 1November 2025 site view 2November 2025 site view 3November 2025 site view 4

October 2025

78%

Core vertical elements progressing

October 2025 site view 1October 2025 site view 2October 2025 site view 3October 2025 site view 4

September 2025

71%

MEP first-fix complete across residential floors

September 2025 site view 1September 2025 site view 2September 2025 site view 3

August 2025

66%

Slab pours advancing on upper floors

August 2025 site view 1August 2025 site view 2August 2025 site view 3

July 2025

60%

Structural works topped out

July 2025 site view 1July 2025 site view 2July 2025 site view 3July 2025 site view 4

June 2025

50%

Foundation works and podium slabs

June 2025 site view 1June 2025 site view 2June 2025 site view 3June 2025 site view 4

Dubai Islands

Allegro Park

Selling NowProject page

November 2025

18%

Excavation and shoring complete

Site excavation reaching final depthShoring walls in place around perimeter

September 2025

8%

Enabling works and site mobilisation

Site mobilisation and hoarding installation